Khaw Boon Wan said Northern General Hospital maybe completed one year earlier than 2010..that is. open by 2009.
WHy wasn't construction started in 2001 as what was perceived as an election promise by Ho Peng Kee?
Ho Peng Kee's promise as good as Kenneth Chen promised to build a swimming pool should he had won at Potong Pasir?
Is Khaw Boon Wan smoking something other than tobacco or blowing smoke out of his orifice only.
Let's calculate the construction schedule as from 01-Sep-2005:
1) 6 month - calling of tender and award piling work and sub-structure work.
2) 9 month - completion of sub-structure work.
3) 24 month - completion of main structure work.
4) 12 month - architectural, mechanical & electrical works, equipment, etc.
5) 9 month - testing, hospital fitting out, training, "soft opening"
That is, all together 60 months as from 01-Sep-2005
...or opening in 01-Sep-2010.
FAT HOPE THAT THE NORTHERN GENERAL HOSPITAL CAN BE OPEN IN 2009...LET ALONE BY 01-JANUARY 2010.
Wonder is this another GE gimmick in readiness of PM Lee ND Rally Speech on 21-Aug...annoucing GE end-2005????
----------------------------------------------------------------------------------
WHy was Northern General Hospital builds so late whereas as early as 2001, the problem was identified that "North" is in dire need of a general hospital.....and Ho Peng Kee promised that if he was elected.
He was re-elected and can't delivered on his promise.
After 2001 Election, two hospitals were planned, i.e. in Jurong and Woodlands or Sembawang. SUpposedly to be at hte Sembawang Hospital site.
Pioneer JC at Jurong East MRT Station was vacated, and the the piling tender for Jurong Hospital was ready to tender......and somewhat stopped in its track. o idea why it was KIV.
SUspect that it was budget cosntraint.......and now you realised that that S$380 million SingTel "writeoff" could very well paid for at least one of these hospital.
[In 1995, 600-bed TTSH construction value (excluding TTSH medical equipment & system} was about S$387 million.]
Then, it was undecided as to whether to locate the other hospital at Woodlands or Sembawang....and as we now know..it is at Yishun, the Northern General Hospital.
The question is:
Why must we the CoOmmon People suffered where as far back as 2001, it was already known that we need another "general hospital" at the "North"?
Poor planning on the part of Khaw Boon Wan...or penny-pinching policy by PM Lee applying his mathematician's trained cold logic and hard-hearted decision that the cost has yet to justify the construction of Northern General Hospital till today?
--------------------------------------------------------------------------------
More goodies to come:
The S$64 million CDC was slated to be constructed in the 90s,..but Asian Financial Crisis put a brake to it..........resulting in a shortage of bed where 600 foreign workers suffering from chicken pox "used up" all TTSH beds.
Next, we do need a Rehabiliation Centre to be constructed at TTSH....to cater for our ageing population.
No money to build but yet PM Goh has "prime-pump" S$600 million into the cosntruction industry in 2004.
We ask ourself again:
Is healthcare not a priority for the ageing populaiton of Singapore.
And it takes those brilliant scholars SIX YEARS to make up their mind to build a Northern General Hospital???
Make one think whether they are earning theri S$1 million+ annual salary or not......as useful as an ICONIC and TALISMANIC President Nathan?
Will Khaw Boon Wan resigned out of shame if the Northern general Hospital is not open for business on 31-December-2009?
And what is the betting that Ho Peng Kee will retire and make way for "new blood" in the forthcoming GE?






